President Obama has chosen federal appeals judge Sonia Sotomayor for the Supreme Court.  The African American Environmentalist Association has an extended discussion of her energy and environmental views, reprinted below:

Judge Sonia Sotomayor [above] wrote an opinion in Riverkeeper v. EPA, 475 F.3d 83 (2d Cir. 2007), that the EPA was not permitted to engage in a cost-benefit analysis to determine “best technology available”; instead, it could consider cost only to determine “what technology can be ‘reasonably borne’ by the industry” and whether the proposed technology was “cost-effective” – which, she concluded, requires the EPA in turn to determine whether the technology at issue is “a less expensive technology that achieves essentially the same results” as the best technology that the industry could reasonably bear.

The case was a challenge to an EPA rule regulating cooling-water intake structures at power plants. To minimize the adverse impact on aquatic life (which could otherwise be trapped against the intake structure or, if small enough, sucked into the pipes themselves), the Clean Water Act requires the intake structures to use the “best technology available,” without specifying what factors the EPA should consider in determining what constitutes the “best technology available.”

Judge Sotomayor explained:

Grist thanks its sponsors. Become one.

“assuming the EPA has determined that power plants governed by the Phase II Rule can reasonably bear the price of technology that saves between 100-105 fish, the EPA, given a choice between a technology that costs $100 to save 99-101 fish and one that costs $150 to save 100-103 fish. . . could appropriately choose the cheaper technology on cost-effectiveness grounds.”

On this issue, Sotomayor remanded to the EPA, finding it “unclear” how the EPA had arrived at its conclusions and, in particular, whether the EPA had improperly weighed costs and benefits.

Sotomayor also held that the EPA could not consider restoration measures — such as restocking fish to compensate for fish killed by an intake system — when determining the best technology available for a particular power plant. Sotomayor wrote that “[r]estoration measures are not part of the location, design, construction, or capacity of cooling water intake structures, and a rule permitting compliance with the statute through restoration measures allows facilities to avoid adopting any cooling water intake structure technology at all, in contravention of the Act’s clear language as well as its technology-forcing principle.” Finally, Sotomayor also determined that, at a minimum, EPA’s determination that the CWA provision at issue applies to existing and new facilities was a reasonable interpretation of the statute.

The industry plaintiffs filed petitions for certiorari, which the Supreme Court granted in April 2008 to review the cost-benefit issue. AAEA attended the December 2, 2008 Oral Arguments at the U.S. Supreme Court. By a vote of 6-3, the Court reversed. In an opinion by Justice Scalia, the majority deemed “[i]t . . . eminently reasonable to conclude that” the CWA’s silence with regard to determining the best technology available “is meant to convey nothing more than a refusal to tie the agency’s hands as to whether cost-benefit analysis should be used, and if so to what degree.” [Source: Supreme Court of the U.S. (SCOTUS) Blog]